The greatest project risk occurs when:
A) the probability of the event is high and the consequences of the event are high.
B) the probability of the event is high and the consequences of the event are low.
C) the probability of the event is low and the consequences of the event are high.
D) the probability of the event is low and the consequences of the event are low.
Correct Answer:
Verified
Q32: Leave it to the Europeans to develop
Q33: An agreement between two firms that has
Q34: There is always a chance that different
Q35: One technique that can be used to
Q36: The greatest project opportunity occurs when:
A)the project
Q38: Project risk is highest during the:
A)termination stage
Q39: The difference between projects that fail and
Q40: The period of highest risk impact for
Q41: A serious risk factor probably has:
A)a high
Q42: A method for conducting risk factor identification
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents