Effective comparative estimates rely most heavily on:
A) an accurate inflation factor.
B) the correct number of years elapsed between the old project and the current one.
C) true comparability between the current project and previous project work.
D) the correct number of employees on the new project compared with the previous one.
Correct Answer:
Verified
Q34: Once most of the design work is
Q45: You are probably looking at a bill
Q47: When asked to provide an estimate of
Q48: An activity with a learning rate of
Q49: It took 66 hours of analysis to
Q51: If it takes 40 hours to complete
Q52: What learning rate is being demonstrated if
Q53: It took 80 hours of analysis to
Q54: A normal cost is incurred when:
A)overtime is
Q55: An activity with a learning rate of