A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?
A) 11,30
B) 7,24
C) 11,24
D) 7,36
Correct Answer:
Verified
Q86: Activities C,D,and E in the project represented
Q87: In general,the better candidates for shortening are:
A)early
Q88: A project's duration can be reduced by:
A)shortening
Q89: Hammock activities allow:
A)project managers to streamline the
Q90: A gentleman farmer maniacally works on academic
Q92: Summaries for some subsets of the activities
Q93: A gentleman farmer maniacally works on academic
Q94: A gentleman farmer maniacally works on academic
Q95: One approach to reducing project length would
Q96: Which technique would accelerate the completion of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents