Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.
A) 12
B) 13
C) 14
D) 15
Correct Answer:
Verified
Q58: Activity Z has estimates a = 5,b
Q59: What is the early start time for
Q60: What is the early finish time for
Q61: Project Test Bank is composed of activities
Q62: Use the network diagram and activity lengths
Q64: Project Test Bank is composed of activities
Q65: Use the network diagram and activity lengths
Q66: Use the network diagram and activity lengths
Q67: Use the information in the table to
Q68: What is the float start time for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents