The term ordered activity means:
A) tasks must either precede or follow other tasks in project planning and management.
B) tasks cannot be performed unless the project manager issues a specific command to perform the work.
C) prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D) tasks are not performed unless the customer issues a specific request to perform the work.
Correct Answer:
Verified
Q22: _ activities have two or more immediate
Q23: Pessimistic and optimistic values are estimated at
Q24: Concurrent activities are:
A)activities that must be done
Q25: An activity with two or more immediate
Q26: The longest route through the network is
Q28: In the beta distribution,the longer tail is
Q29: _ activities have two or more immediate
Q30: Because an activity's pessimistic estimate may represent
Q31: Thanks to excessive dilly dallying,the subcontractor grossly
Q32: Serial activities are those that:
A)flow from one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents