In the analytical approach,the probabilities of completing the project within a certain time are computed assuming that ________.
A) the expected project completion time is the product of the expected activity times along the critical path,which is found using the expected activity times
B) the variance of the distribution is the sum of the variances of those activities along the critical path,which is found using the expected activity times
C) the variance of the distribution is the sum of the variances of those activities along the critical path,which is found using the variances of activity times
D) the distribution of project completion times is not known
Correct Answer:
Verified
Q73: Define risk and risk analysis.
Q74: In Crystal Ball,the output variables in which
Q75: Running the Tornado Charts tool before the
Q76: In Crystal Ball,Latin Hypercube sampling results in
Q77: List the steps used in Crystal Ball
Q79: In Crystal Ball,Monte Carlo sampling divides each
Q80: Assumption cells in Crystal Ball can be
Q81: Explain how to fit distributions with Crystal
Q82: Explain the procedure associated with Decision Table
Q83: How does the Scenario Analysis tool in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents