Use the case below to answer the following question(s) .
S&N Manufacturing makes four different steel sheets,A,B,C,and D,with different percentages of iron.Each sheet must flow through five departments,forming,rolling,sintering,painting,and quality check.The table below shows the relevant data.Production rates are shown in units/hour.(Sheet A uses imported steel and does not require rolling.)
S&N wants to determine the number of steel sheets to produce in order to maximize monthly profit.
Let A,B,C,and D denote the number of units of model A,B,C,and D to be produced,respectively.
-Which of the following is the inequality/equality that describes the time constraint of the painting department?
A) A/30 + B/30 + C/35 + D/25 ≤ 330
B) B/30 + C/20 + D/20 = 330
C) A/70 + B/50 + C/50 + D/44 = 330
D) A/60 + B/60 + C/70 + D/50 ≤ 330
Correct Answer:
Verified
Q56: Use the case below to answer the
Q57: Use the case below to answer the
Q58: Use the case below to answer the
Q59: Use the case below to answer the
Q60: Use the case below to answer the
Q62: Use the case below to answer the
Q63: Use the case below to answer the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents