All of the following describe the appropriate application of Perform Quantitative Risk Analysis in project management EXCEPT:
A) Large, complex and risky projects stand to benefit from the additional rigor of quantitative risk analysis techniques.
B) Quantitative techniques are used when it is critical to predict the probability of completing a project on time or within budget with confidence.
C) Brainstorming techniques are used by the team and other stakeholders to identify as many project risks as possible.
D) Monte Carlo Simulation and Fault Tree Analysis are examples of useful quantitative risk analysis techniques.
Correct Answer:
Verified
Q25: Which of the following accurately describes risk
Q26: All of the following criteria can be
Q27: Project managers can identify risks by learning
Q28: Which of the following activities illustrates a
Q31: When a project team elects to purchase
Q32: Project teams can often identify risks by
Q33: Which of the following describes the activities
Q34: Which of the following activities illustrates a
Q34: Risk is often considered in terms of
Q35: Which of the following describes the appropriate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents