All of the following elements should be included in a project scope statement EXCEPT:
A) the project work statement
B) names of the project team members
C) assumptions and constraints that may limit or influence project work
D) key deliverables with acceptance criteria
Correct Answer:
Verified
Q22: A deliverable at the lowest level of
Q33: Work Breakdown Structures can be displayed in
Q34: For each component in the Work Breakdown
Q35: Formally documented procedures that define how project
Q36: Which of the following items best depicts
Q37: Which of the following items best describe
Q40: Subject matter experts can provide invaluable assistance
Q41: A typical change request form will include
Q42: When developing a Work Breakdown Structure (WBS)for
Q43: What is "scope creep"? What actions can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents