Communications to stakeholders are necessary for which of the following reasons?
A) to help them make good decisions
B) to keep them at arms length so progress can continue
C) to shift the burden of risk from the project team to the stakeholders
D) to provide input to team performance reviews
Correct Answer:
Verified
Q32: All of the following statements accurately describe
Q33: Which of the following activities can be
Q34: Project management plans generally include all of
Q35: Which of the following statements accurately describes
Q36: The project communications matrix lists important "who,"
Q37: Stakeholders include all of the following people
Q38: Communications from stakeholders are important for all
Q40: Which of the following statements accurately describes
Q43: Describe how you would use the plan-do-check-act
Q44: Describe the approach you would use to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents