A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by as hammock activity. Which is a legitimate hammock activity for this project?
A) combine activities A, B, C
B) combine activities B, E, H
C) combine activities E, F
D) combine activities G, H, I
Correct Answer:
Verified
Q68: A project has the precedence requirements and
Q69: Use the network diagram and activity lengths
Q70: Activities C, D, and E in the
Q72: Use the network diagram and activity lengths
Q74: Project Test Bank is composed of activities
Q75: Activities C, D, and E in the
Q76: Project Test Bank is composed of activities
Q89: Hammock activities allow:
A)project managers to streamline the
Q92: Summaries for some subsets of the activities
Q95: One approach to reducing project length would
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents