A Project Has the Precedence Requirements and Activity Durations Shown

Question 73

Multiple Choice

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by as hammock activity. Which is a legitimate hammock activity for this project? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by as hammock activity. Which is a legitimate hammock activity for this project?   A)  combine activities A, B, C B)  combine activities B, E, H C)  combine activities E, F D)  combine activities G, H, I


A) combine activities A, B, C
B) combine activities B, E, H
C) combine activities E, F
D) combine activities G, H, I

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents