Solved

Hammock Activities Allow

Question 89

Multiple Choice

Hammock activities allow:


A) project managers to streamline the linkage and sequencing between activities.
B) project workers to effectively skip nonessential activities without compromising project quality.
C) the project team to better disaggregate the overall project network into subsets.
D) the project manager to identify float more quickly and leverage it more successfully for the overall success of the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents