There's an Old Saying,"The Job Is Not Finished Until the Paperwork

Question 78

Multiple Choice

There's an old saying,"The job is not finished until the paperwork is done." From an activity network standpoint,this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed.It might be possible to work on some paperwork as early activities are completed.In order to depict this in an activity network:


A) hammock activities could be drawn.
B) subroutines could be added.
C) shortcuts can be added to the network.
D) laddering could be used to redraw the network.