Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:
A) the project activity of Material Delivery was pretty close to the optimistic estimate.
B) the project activity of Material Delivery was pretty close to the most likely estimate.
C) the project activity of Material Delivery had a much higher variance than anticipated.
D) the project activity of Material Delivery was pretty close to the pessimistic estimate.
Correct Answer:
Verified
Q24: The variance of an activity is given
Q38: _ activities can be used as summaries
Q39: There is no slack on the project
Q40: One of the defining points of a
Q42: An activity has a pessimistic time that
Q44: The length of time expected to complete
Q45: What is the late start time for
Q46: An activity has an optimistic time estimate
Q47: Based on the activity network pictured,what is
Q48: An activity has an optimistic time estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents