A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology?
A) 13.5
B) 22.5
C) 11.25
D) 9.0
Correct Answer:
Verified
Q66: A system-wide constraint is called a(n):
A) rope.
B)
Q66: CCPM advocates performing all non-critical activities:
A)as late
Q67: Use the project information in the table
Q70: Use the project information in the table
Q73: A project consists of six consecutive tasks
Q74: A project consists of six consecutive tasks
Q76: The buffers supplied to non-critical paths in
Q76: Use the project information in the table
Q77: Subcontractor deliveries are difficult to schedule with
Q84: Which of the following statement is best?
A)The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents