An important departure from traditional project management is that critical chain project management logic:
A) changes from a late finish to an early start approach.
B) factors in the effects of resource contention.
C) adjusts expected activity durations to reflect a 95% probability of completion on time.
D) creates a separate safety margin for each activity in the project.
Correct Answer:
Verified
Q41: Your next project consists of 5 consecutive
Q57: Your next project consists of 8 consecutive
Q67: A project consists of six consecutive tasks
Q68: Which statement about critical chain methodology is
Q69: A project consists of three activities with
Q71: A project consists of four consecutive tasks
Q73: A project consists of three activities with
Q75: A project consists of three activities with
Q76: The buffers supplied to non-critical paths in
Q77: Subcontractor deliveries are difficult to schedule with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents