Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) the project manager cannot force subcontractors to use this project management approach.
B) the feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) subcontractors routinely operate according to calendar delivery dates.
D) the corporate culture of "no blame" does not naturally extend to subcontractors.
Correct Answer:
Verified
Q57: Your next project consists of 8 consecutive
Q72: An important departure from traditional project management
Q73: A project consists of three activities with
Q75: A project consists of three activities with
Q76: The buffers supplied to non-critical paths in
Q78: A project consists of six consecutive tasks
Q79: Which of the following statements about CCPM
Q80: A project is represented by the activity
Q81: Successful implementation of CCPM depends on first:
A)identifying
Q82: When choosing the most viable solution to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents