All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 20% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.The executive level of the organization just completed a retreat where they read The One Minute Manager,Who Moved My Cheese,and Critical Chain.They return from their retreat both energized and much wiser in the ways of project management.They know that everyone has been routinely adding 20% and want to scale the project back to an unpadded estimate.How much should they cut?
A) 42%
B) 60%
C) 33%
D) 27%
Correct Answer:
Verified
Q47: Your next project consists of 10 consecutive
Q55: Under the student syndrome model,the slope of
Q56: If a project activity experiences negative variation:
A)the
Q57: All five members of a project team
Q58: If a project activity experiences positive variation:
A)the
Q59: A worker is assigned three tasks,A,B,and C,each
Q61: A project consists of three activities with
Q62: A project is represented by the activity
Q63: A project consists of four consecutive tasks
Q64: A project is represented by the activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents