All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 20% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.Much to his surprise,top management cuts only 10% off his time estimate.How much of a cushion is now built into the project?
A) 62%
B) 74%
C) 56%
D) 42%
Correct Answer:
Verified
Q52: A worker is assigned three tasks,A,B,and C,each
Q53: Which tendency is NOT a contributing factor
Q54: When individual activity lengths are overestimated:
A)their individual
Q55: Under the student syndrome model,the slope of
Q56: If a project activity experiences negative variation:
A)the
Q58: If a project activity experiences positive variation:
A)the
Q59: A worker is assigned three tasks,A,B,and C,each
Q60: All five members of a project team
Q61: A project consists of three activities with
Q62: A project is represented by the activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents