If an activity's progress is defined as 0% until the moment is complete, the project manager is using:
A) the 50/50 rule.
B) the all or nothing rule.
C) the 0/100 rule.
D) the Do Not Pass Go rule.
Correct Answer:
Verified
Q68: Use the earned value table for Project
Q73: Project Terrace has an actual cost of
Q78: In earned value management,schedule variance is defined
Q82: Very short work packages would be better
Q84: In the formation stage,failed projects are more
Q88: The critical success factor that relates to
Q91: Funding problems are a key success inhibitor
Q94: Each activity contained a series of milestones
Q96: An unmotivated team is a key success
Q97: One of these things is NOT like