The earned value divided by the actual,cumulative cost of the work to date is the:
A) cost performance index.
B) budgeted cost at completion index.
C) budget efficiency index.
D) schedule performance index.
Correct Answer:
Verified
Q23: How does a tracking Gantt chart's appearance
Q54: Milestones are generally considered to be:
A)demotivators for
Q55: Take the factors considered by earned value
Q56: A project manager can calculate the projected
Q58: A tracking Gantt chart does NOT allow
Q60: A project manager that uses milestones as
Q61: Use the earned value table for Project
Q62: Use the data to calculate the earned
Q63: Use the data to calculate the earned
Q64: At the end of week 10,this project