An ex-gratia claim made when a project is closed down is made when:
A) there is no contractual basis for a claim.
B) the project company fails to perform to the terms of the contract.
C) the client company fails to perform to the terms of the contract.
D) a third party causes either the client or project company to fail to perform to the terms of the contract.
Correct Answer:
Verified
Q85: Which of these concerns does NOT belong
Q86: Projects accumulate quantities of unused supplies and
Q87: The Microserf was in a blind panic;now
Q88: A final report section on the techniques
Q89: When a project is shut down,the project
Q91: In non-binding arbitration:
A)the judge can offer suggestions
Q92: An example of an external intellectual issue
Q93: Many times,clients will shift new people into
Q94: An internal intellectual issue that arises when
Q95: The final project report should answer questions
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents