Figure 11-1 -Given the Network Shown in Figure 11-1,assume That Completion of That

Question 117

Multiple Choice

Figure 11-1 Figure 11-1   -Given the network shown in Figure 11-1,assume that completion of B is delayed by two days.What happens to the project? A) The critical path is extended by two days. B) The start of activity F is delayed by two days. C) The start of activity E is delayed by two days. D) All of the above E) None of the above
-Given the network shown in Figure 11-1,assume that completion of B is delayed by two days.What happens to the project?


A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents