Table 11-1
The following represents a project with known activity times.All times are in weeks.
-Using the data in Table 11-1,what is the minimum possible time required for completing the project?
A) 8
B) 14
C) 25
D) 10
E) None of the above
Correct Answer:
Verified
Q47: Given the following small project,the critical path
Q48: According to Table 11-1,compute the slack time
Q49: Managers use the network analysis of PERT
Q50: Given an activity's optimistic,most likely,and pessimistic time
Q51: Given an activity's optimistic,most likely,and pessimistic time
Q53: Given the following small project,the critical path
Q54: Which of the following is not a
Q55: The first step in planning and scheduling
Q56: Table 11-2
The following represents a project with
Q57: Given an activity's optimistic,most likely,and pessimistic time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents