Many projects ____ because of scope creep caused by additional work that was not documented or approved, or was not communicated and in turn caused errors or rework for other elements of the project.
A) overspend their budget or are not completed on time
B) are completed early and under budget
C) are accepted and renewed
D) are not contracted
Correct Answer:
Verified
Q92: The _ all of the lowest-level work
Q93: The WBS should be decomposed to a
Q94: The project team or contractor must avoid
Q95: Having other project team members participate in
Q96: The _ states the specific deliverable that
Q98: Quality standards that will be used should
Q99: It is important to plan for _
Q100: A comprehensive project scope document is _
Q101: It is common to progressively elaborate the
Q102: The responsibility assignment matrix may use a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents