If ____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time.
A) total time
B) free time
C) total slack
D) cumulative slack
Correct Answer:
Verified
Q78: Positive slack indicates the maximum amount of
Q79: Negative slack indicates a lack of slack
Q80: The project control process involves all of
Q81: The project control process starts with establishing
Q82: The facilitator for the Scrum development process
Q84: A regular _ should be established for
Q85: The _ involves regularly gathering data on
Q86: Earliest finish time (EF)is calculated _.
A) by
Q87: The development team develops, delivers, and demonstrates
Q88: The _ and _ times are determined