When considering the availability of resources, it may be necessary to make some assumptions, such as
A) the unemployment rate in the community.
B) the ability to hire additional individuals with the appropriate expertise in time for when they will be required to work on a project.
C) the number of project deliverables.
D) the type of organizational structure of the sponsor.
Correct Answer:
Verified
Q27: The estimated types and quantities of resources
Q28: It is necessary to monitor the progress
Q29: An updated project schedule can be generated
Q30: Changes requested early in the project always
Q31: In many cases, especially for smaller projects,
Q33: The estimated duration for each activity must
Q34: Once this baseline plan is agreed upon
Q35: It is important to know what types
Q36: Throughout a project, changes may occur that
Q37: When estimating the types and quantities of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents