In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?
A) Activities that use the same resource may not be able to occur in parallel to each other.
B) Activities that use different resources may be shown in a serial relationship.
C) The activities could be shown in a loop relationship.
D) Resources that are unlimited are not shown in a resource assignment.
Correct Answer:
Verified
Q1: Resource-limited scheduling is a method for
A) developing
Q3: If resources are to be considered in
Q4: A resource requirements plan illustrates
A) who is
Q5: The start of noncritical activities are delayed
Q6: At a minimum, network diagrams illustrate the
Q7: _ assist with the complexity of generating
Q8: Resource utilization charts based on each activity's
Q9: The statement, "Network diagrams illustrate the technical
Q10: In resource-limited scheduling, the lower priority activities
Q11: Why are activities drawn in a serial
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents