The To-Complete Performance Index Is

Question 81

Multiple Choice

The to-complete performance index is


A) the amount of funds remaining for the project.
B) the rate of performance required for the remaining work to finish the project within budget.
C) the ratio of committed costs remaining to planned costs.
D) the ratio of planned costs for the work remaining to the budgeted costs of the project.