Committed Costs in a Project Are

Question 99

Multiple Choice

Committed costs in a project are


A) those costs budgeted for the scheduled activities.
B) planned value of the project.
C) budgeted costs of the work scheduled.
D) the amounts that have been obligated or encumbered for materials, equipment, or services.