The cumulative budgeted cost is
A) the aggregate estimated costs of all the activities.
B) the amount budgeted to accomplish the work scheduled to a point in time in the project.
C) the committed costs for an activity.
D) the sum of all the funds expended to a point in time in the project.
Correct Answer:
Verified
Q86: The earned value is
A) the budgeted cost
Q87: The cumulative earned value of the project
Q88: The cumulative actual costs of a project
Q89: The forecasted cost at completion is
A) a
Q90: The key to managing a cash flow
Q92: The actual cost on a project is
A)
Q93: If the project has a negative cost
Q94: The positive cost variance means
A) more money
Q95: For a project, the TBC = $200,000,
Q96: The key to managing _ is to