Calculate the forecasted cost at completion if the cumulative actual cost is $10,000 and the re-estimate of remaining work to be performed is $5,000.
A) FCAC = $5,000
B) FCAC = $15,000
C) FCAC = 2
D) FCAC = 0.5
Correct Answer:
Verified
Q56: The cost performance index (CPI)is a measure
Q57: A second method for determining the forecasted
Q58: Calculate the forecasted cost at completion if
Q59: Plot _ curves on the same graph
Q60: Determining the earned value involves collecting data
Q62: Allocating total project costs for the various
Q63: Once the project starts, it is necessary
Q64: The _ is the amount that is
Q65: The _ is a measure of the
Q66: _ is the value of the work