Consider a project that involves painting five similar houses over ten weeks (one house every two weeks) for a total budgeted cost of $20,000.The budget is $4,000 per house.At of the end of week 5, you determine that $10,000 has actually been spent and three houses have been painted completely. What is the earned value of the project?
A) $10,000
B) $12,000
C) $4,000
D) $20,000
Correct Answer:
Verified
Q40: The budget for each work package is
A)
Q41: A method for calculating the forecasted cost
Q42: Earned value, the value of _, is
Q43: The _ is the sum of the
Q44: If the cumulative earned value is $10
Q46: Calculate the forecasted cost at completion if
Q47: Costs are _ when an item is
Q48: The _ is the amount that was
Q49: It's important that the person estimating the
Q50: Calculate the cost variance if the cumulative
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents