A Cost Is Determined for Each Period, Based on When

Question 21

Multiple Choice

A cost is determined for each period, based on when the activities that make up the work package are scheduled to be performed, to create


A) the time-phased budget.
B) the actual costs of the project.
C) an example budget.
D) an adjusted budget.

Correct Answer: