Risk response planning involves all the following except
A) developing an action plan to reduce the likelihood of occurrence or potential impact of each risk.
B) establishing a trigger point for when to implement the actions to address each risk.
C) assigning responsibility to specific individuals for implementing each response plan.
D) brainstorming the possible risks that could occur in the project.
Correct Answer:
Verified
Q56: The _ should be those that are
Q57: A good forum for regularly reviewing, updating,
Q58: The trigger point in the risk response
Q59: _ risk involves determining the likelihood that
Q60: A realistic approach to managing risk is
Q62: Which of the following is not an
Q63: A possible action trigger for rain or
Q64: The possible response plan for vendor delay
Q65: A risk is
A) an uncertain event that,
Q66: The possible impact for rain or snow
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents