Figure 12-1 -Given the Network Shown in Figure 12-1, Assume That the Assume

Question 88

Multiple Choice

Figure 12-1 Figure 12-1   -Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four days. What changes will take place? A)  The critical path will change to: A-C-B-D-E-F-H. B)  Activity F will be delayed by four days. C)  Activity E will be delayed by four days. D)  Activity G will be delayed by four days. E)  None of the above
-Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four days. What changes will take place?


A) The critical path will change to: A-C-B-D-E-F-H.
B) Activity F will be delayed by four days.
C) Activity E will be delayed by four days.
D) Activity G will be delayed by four days.
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents