Table 12-3
-According to Table 12-3, there are five activities in a PERT project. What is the variance of the critical path?
A) 5.222
B) 4.222
C) 1.222
D) 0
E) 1.111
Correct Answer:
Verified
Q65: Your company is considering submitting a bid
Q69: The two common techniques for drawing PERT
Q70: Table 12-3 Q70: In a PERT network,the latest (activity)start time Q71: In PERT,we assume that Q75: The project described by: Q76: The work breakdown structure involves identifying the Q77: The project described by: Q78: In PERT analysis,the probability of the optimistic Q78: Table 12-3 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents