Table 12-1
The following represents a project with know activity times. All times are in weeks.
-Using the data in Table 12-1, compute the latest finish time for activity E.
A) 4
B) 10
C) 14
D) 25
E) None of the above
Correct Answer:
Verified
Q14: PERT stands for Probabilistic Evaluation and Review
Q17: Given the assumptions in PERT, the probability
Q38: Slack is the time an activity can
Q39: CPM stands for Comprehensive Project Method.
Q41: Table 12-1
The following represents a project with
Q41: Given an activity's optimistic,most likely,and pessimistic time
Q45: Table 12-2
The following represents a project with
Q46: Table 12-2
The following represents a project with
Q47: Given the following small project, the critical
Q50: Given an activity's optimistic,most likely,and pessimistic time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents