The expected time in PERT is
A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B) the modal time of a beta distribution.
C) a simple average of the most optimistic, most likely, and most pessimistic times.
D) the square root of the sum of the variances of the activities on the critical path.
Correct Answer:
Verified
Q26: Given an activity's optimistic, most likely, and
Q27: The value of work completed is computed
Q28: CPM
A)assumes we do not know ahead of
Q29: Gantt charts contain information about the time
Q30: The first step in planning and scheduling
Q32: The activity crash cost is equal to
Q33: The activity difference is the actual duration
Q34: Given an activity's optimistic, most likely, and
Q35: Budgets are computed using only ES times.
Q36: PERT
A)assumes that we do not know ahead
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents