Lead Time for Computers Is 7 Days with Daily Demand

Question 62

Multiple Choice

Lead time for computers is 7 days with daily demand of 5 computers and a safety stock of 1 day. Each kanban holds 8 computers. What is the correct number of kanbans?


A) not enough information
B) 1
C) 5
D) 7
E) 8

Correct Answer: