Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity __________ should be crashed first, adding __________ to project cost.
A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or two should be crashed; $1,400
Correct Answer:
Verified
Q61: A local project being analyzed by PERT
Q64: A contractor's project being analyzed by PERT
Q65: _ is an organization formed to ensure
Q66: A project whose critical path has an
Q69: If an activity whose normal duration is
Q74: What is the objective of critical path
Q87: Analysis of a PERT problem shows the
Q87: Identify and describe briefly each of the
Q105: The _ distribution is appropriate for calculating
Q113: What was the name of the construction
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents