Which of the following statements regarding CPM is true?
A) The critical path is the shortest of all paths through the network.
B) The critical path is that set of activities that has positive slack.
C) Some networks have no critical path.
D) All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
E) All of the above are false.
Correct Answer:
Verified
Q18: The phases of project management are:
A) planning,
Q22: Which of the following is not one
Q23: Which of the following statements about Bechtel
Q26: Match the following steps in Microsoft's development
Q30: The main difference between PERT and CPM
Q36: A project organization
A) is effective for companies
Q51: Which of the following statements regarding critical
Q69: The standard deviation of project duration is
Q76: In PERT analysis, the identification of the
Q109: A project manager is interested in crashing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents