A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product: For output to equal projected demand,what will be the idle time at the second workstation of the assembly line that uses the minimum number of workstations?
A) 0 seconds
B) 1 second
C) 2 seconds
D) 3 seconds
E) 5 seconds
Correct Answer:
Verified
Q141: A company needs to locate three departments
Q142: A company needs to locate three departments
Q143: A company needs to locate three departments
Q144: Given the following line balance data:
Q145: A company needs to locate three departments
Q147: A company needs to locate three departments
Q148: A company needs to locate three departments
Q149: A company needs to rebalance a product
Q150: A company needs to locate three departments
Q151: A company needs to locate three departments
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents