A project consists of nine major activities,as shown.There are three separate paths in the network: a-c-f,b-d-g,and e-h-i.
(i)What is expected project duration time?
(ii)Determine the probability that the project will take more than 35 weeks to complete.(All durations are in weeks.)
11eab92b_c477_d00e_99e6_ad14123209e7
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q115: A project has the activities and activity
Q116: Determine the amount of slack in each
Q117: Using the information given,do the following:
(i)Identify the
Q118: A project superintendent is about to begin
Q119: The manager of a National Forest is
Q121: What activities make up the critical path?
Q122: Indirect cost for a project is $2500
Q123: What is the total cost of reducing
Q124: What is the total cost of reducing
Q125: What are the estimated slack times (in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents