The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities: What is the estimated slack time for the path U-W-Z?
A) 0 days
B) 25 days
C) 35 days
D) 45 days
E) 85 days
Correct Answer:
Verified