The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities: What is the estimated expected (mean) duration for activity Y?
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer:
Verified