Which of the following is NOT a secondary characteristic of a typical project?
A) Each project must have a primary sponsor or champion.
B) A project usually cuts across organizational lines.
C) A project consists of team members who all report to the same manager.
D) Projects must do something, must have an output or deliverable.
Correct Answer:
Verified
Q69: Project management is defined as a process
Q70: Projects must have closure in order to
Q71: IT projects are unique, requiring special tools
Q72: If any of the project constraints changes
Q73: Project management requires a diverse set of
Q74: All projects are constrained by their scope,
Q75: If the project allows changes and new
Q77: IT projects are growing in size, complexity,
Q78: Progressive _ is a concept that refers
Q79: IT organizational structure change(s) can help IT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents