Which of the following is NOT an element of the staff management plan?
A) The process to follow when adding or removing people from the project
B) Any safety issues that need to be followed
C) The list of specific names of the initial people assigned to the project
D) Specific risks associated with assigned human resources
Correct Answer:
Verified
Q62: Authority is defined as either legal or
Q63: _ managers receive support because the project
Q64: A responsible party is assigned to each
Q65: Which of the following is NOT one
Q66: If working overtime becomes the norm, stakeholders
Q68: _ means that the whole is greater
Q69: Working _- whether compensated or not-on a
Q70: According to Douglas McGregor, _ workers are
Q71: A project manager must figure out what
Q72: Which of the following is NOT a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents