The acronym PERT stand for:
A) Program Estimation and Review Technique
B) Program Evaluation and Risk Technique
C) Program Event and Review Technique
D) Program Evaluation and Review Technique
Correct Answer:
Verified
Q68: Resource _ defines the amount of time
Q69: Resource _ is the process of rescheduling
Q70: The critical _ method, unlike the critical
Q71: The output from _ planning is used
Q72: Which of the following is NOT an
Q74: What is the critical path of a
Q75: CPM produces what key piece of information?
A)
Q76: Crashing and _ are techniques used to
Q77: What is the deliverable from the project
Q78: This is the cost of a human