________ is defined as the amount of elapsed time it will take the resource to complete the work.
A) Estimate
B) Duration
C) Effort
D) Demand
Correct Answer:
Verified
Q38: The critical path method, unlike the critical
Q39: COCOMO is an acronym for the Constructive
Q40: Function point analysis can be done at
Q41: _ is defined as the actual amount
Q42: _ task dependencies are defined based on
Q44: The precedence diagram method (PDM) of constructing
Q45: _ task dependencies are based on work
Q46: Time and cost estimates should be done
Q47: Sunken costs are all costs incurred over
Q48: The final deliverable from the activity sequencing